APO MATP Question

Former Member
0 Kudos

Hi Experts,

I have couple of queries related to APO MATP functionality .

System details -

Component version: SAP SCM 5.10

Patch Level : 7

Query 1)

On triggering multilevel ATP check thorugh Sales Order, system is not adjusting

the Header material availability date based on the component availability date .

System is calculating Requirement date for the component based on Header material

SO requirement date and checking the component availability . If the component is not

available by that date, ATP is failing and I am getting list for the component . I want

system to move the Header material to future.

Pls. note that we have RBA activated for the Header material and Output of successful

ATP is confirmed SO.,Planned Order for the Header material , Stock transfer requisition

between RBA locaions and dependent requirement for the component.

Query 2)

We have doing Product Allocation (first check), Multilevel Product Availability

check ( Second Check ) .

ATP check can fail because of Production allocation failure or because of missing

components . Also there could be delay.

I have enabled ATP alert in the check instruction , however I don't see the alerts in the

Alert Monitor. It shows in the ATP overview screen duing ATP check I have enabled

only the standard ATP Alerts .

Pls. share if you know how to make it work with standard SAP ?

Thanks

Prakash

Accepted Solutions (1)

Accepted Solutions (1)

pavan_verma2
Contributor
0 Kudos

Hi Prakash,

There can be allocation constrained due to which you are not confirmation of header material in future.

try to check with deactivating allocation, either remove allocation procedure from product master in APO or use a requirement type--requirement class which does not have allocation.

Thanks,

Pavan Verma