Hi,

Can you explain what is ME58 use for

regards,

zafar

Accepted Solutions (1)

Accepted Solutions (1)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

ME58 allows to pick assigned requisitions and manually convert them into POs. First you enter the criteria to select the purchase requisitions. These are then grouped by vendor (and contract). Example: manually selects a vendor to process & select order type, purchasing group etc., copy the requisition lines into the PO and save.

Note:

ME59 selects requisitions and lists the ones it was able to convert into POs.There is a difference on the level of control between the two transactions and businesses using ME59 should put a manual review step in if they are converting requisitions generated from MRP.

Regards,

Biju K

Former Member
0 Kudos

Hi,

Thanks for your reply,

I want to know if i have 5 PR containing one item in each PR how to create only One PO ref. to that 5 PR.

regards,

zafar

Former Member
0 Kudos

Check

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Zafar,

This transaction is to create the PO from assigned PR.First PR is created then in ME57 you can assign soruce of supply and then in ME58, PO is cretaed from this PR . The new transaction for this is ME59N