on 10-28-2009 10:08 PM
HI,
The Secondary CE iwith category 43 is used for internal activity Allocation .
we have multiple labor activities based on Skill set liek Painitng, Grinding,engine works,Extrior works.
Is it advisable to have same Sec cost element for all or
to keep separate Sec CE for each Activity type. WHat are the pros and cons Please.
If we use a cost element for an activity type is it possible to change it later ( after using the activity type for awork center)
Regards
Chitra
Dear Chitras,
Its depend on routing. In work center u cant assign more than 6 activities in Work Center.
Raj