Hi,
We are using ECC 6.0 and SRM 5.0.
Which flags should be set in SRM when raising an ERS PO.
The options are:
PO Response
Shipping Notif.
Confirm Performance of Service/Goods Receipt
Invoice Expected
Confirmation-Related Invoice Verification
Automatic Settlement
Which flags should be set for normal MIRO invoice matching?
What do they all mean?
Thanks in advance.
Hi,
PO Response -- flag if you are expecting a response to PO to be entered in the sytem
Shipping Notif. --flag if you are expecting a shipping notification to be sent by u r vendor
Confirm Performance of Service/Goods Receipt --- flag if u are excpecting a GR
Invoice Expected -- flag if u are expecting a invoice documnet
Confirmation-Related Invoice Verification -- check for GR based invoice verification
Automatic Settlement - for ERS
Thanks
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.