on 10-27-2009 12:09 PM
Hi Guru's
We want to record results in Plant Maintenance thru T-code QA32 for printing of calibration certificates. Please proivde process for the same.
Regards
Param
Hi Paramjit,
Please check the link it has standard steps for calibration.
http://wiki.sdn.sap.com/wiki/display/ERPLO/Calibrationoftest+equipment
Regards,
vj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I will try to explain you in simple ways...
Create Equipment using IE01 Tcode.
Create a Task list using IA01 or IA05,maintain the Characteristics which you want to check
create a Maint plan using IP01
Now schedule equipment through IP10
This will create a Inspection lot of 14 Type.
Now carry out Result Recording for each char' through QA32
Click on Inspection results printout.You will get the results recorded
You can also use QGp1 or QGP2 etc for the same.
printing of calibration certificates is not standard fumctionality in SAp.You have to customize the program for the same.
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii,
For RR for Plant maintebnance , Goto QE51N ---> Select Equipment / Functional location tab -->Select lot based on Inspection lot Date./ Work center .
with regards,
K.Lokesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.