Hi all

There is a requirement on which I'm currently working

Material A - ROH

MRP type VB

we are maintaining reorder point,safety stock,Maximum stock level

Lot size as HB and Ind/collective ind set as "1"

And in configuration of MRP type VB under "Additional external requirements in reorder point planning"- we have activated

Order reservation,pch req rel etc

This material A is child for 2-3 semi finished materials say B,C,D

When a prod order is created for B,C,D it results in order reservation for Material A(visible in MD04)

Now when we go for MRP run it consolidates the order reservation requirements and it adds up to the normal calculation which it perform in Re order Point plannig(like considering stock level,saftey stock,re order point,max stock level) and gives us a single pruchase req but the requirement is individual purchase req's(for each order reservation element) as we get with standard MRP type - PD

Just want to find out if there is a way to achieve else a confirmation that standard ROP planning in SAP will give only a consolidated single purch req

Appreciate your early response

Please revert if you need any clarifications

Thanks