Dear Friends,

I am facing following isues in workforce planning.

1) I am not able to assign team maintained at WBSE level in assigned activities.Though the manpower maintained at Work Center is easily asigned.

2) The capacity requirement for activity as well as resource in not getting distributed, though I am using Distribution key to distribute work equally both at activity & work center level.

3) Last, once a resource has been assigned to a particular activity for a particular period, the system is still allowing allotment of same resorces to other activities during same period.

Please provide your valuable inputs.

Regards,