Hi,

AS when we run the MRP depending on the material order, saftey stock etc. PR is generated after MRP RUN but for a single material we are getting many PR is there any setting that after MRP Run all the required quantity should come under one PR or can we do it while converting PR into PO .

regards,

zafar

Accepted Solutions (0)

Answers (3)

Answers (3)

pardeep_malik
Active Contributor
0 Kudos

HI,

please refer

Regards,

Pardeep Malik

Former Member
0 Kudos

Hi,

I have checked innmRP4 view present it is balk Individual and collective requirements, and there is 1 and 2 for individual and collective req. only.

if i set it for 2 will i get the single PR for each item ?

regards,

zafar

Former Member
0 Kudos

Dear Zafar,

Try it to two & IF no result

then plz check the link provided by other forum Friend

ur issue should be resolved by that link

and if possible mainatin lot size as MB ( Monthly lot size)

All The Best

Regards

kumar

pardeep_malik
Active Contributor
0 Kudos

Hi,

In MRP1, maintain Lot size as WB.

System will create one PR for one material for One Week.

Regards,

Pardeep Malik

Edited by: Pardeep Malik on Oct 24, 2009 4:07 PM

Former Member
0 Kudos

Hi,

I have checked innmRP4 view present it is balk Individual and collective requirements, and there is 1 and 2 for individual and collective req. only.

if i set it for 2 will i get the single PR for each item ?

regards,

zafar

Former Member
0 Kudos

Dear Zafar,

Plz mainatin lot size as MB or WB

so that sytem will creat PR either weekly or Montly

and just check the link provided By Mr. pradip

in that link all PP experts answers are availble

Regards

kumar

Former Member
0 Kudos

Thanks all.

Former Member
0 Kudos

Hi,

Are all the generated PR's for the same quantity?

Check if you have a lot sizing parameter in the MRP1 view of the said material

~p

Former Member
0 Kudos

Dear Zafar,

1) Just Go to MRP- 4 view, for this particular materail

2) Here u can find the field, Individual/coll

3) here input as 3 ( i.e Collective Requirments only)

4) Now Re- Run MRP with the parameter Planning mode as 3 ( i.e delete & recreat planning data)

Now You can get one PR