on 10-16-2018 5:01 AM
Dear Experts,
I want to ask about schedule line and PR by MRP run.
I have condition that after schedule line is created after MRP run (MD02),
there is another demand ( example : reservation) and we execute MRP run again.
After second MRP run, schedule line is not created but Purchase Requsition (PR) is created.
Why this PR is created? Meanwhile I set valid schedule agreement and source list date.
Please help.
Thanks
Anita
Hi Anita Arifin,
how are you able to make system to consider demand 1 in first MRP run, and consider demand 2 in second MRP run.
Regards,
mahesh Kumar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anita,
1. check the Source list MRP as " 2"
2. check your Requirement date (Backward Scheduling ). probably Requirement date falls before Source list start date.
Best Regards,
Kumar semmalai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.