Hi Gurus,

I have a question regarding the link of Purchase Order and Inbound delivery completed indicator.

This is my scenario. I had created a purhase order with qty 10, then i created a Inbound delivery with 8 qty then i did GR with reference to inbound delivery. Then looking at the purchase order , the PO is set to Delv. Completed. Looking also in the doc flow of the inbound delivery, the status is "complete".

Now , my question, if i go to VL31N and input the purchase order , i am still able to see the open qty which is "2". Is there is no way that the SAP will prompt me after i input the PO number in the VL31n as " Delivery completed" message or someting related to that. Since , in the PO its already Delv. completed?