1.jpg2.jpg3.jpg4.jpgHello everyone,

In process order when i release the each phase i want to generate a PI sheet .

(Example: I have 5 phases/operations. I want 5 PI sheets)

So how should i assign the phases to get the individual PI sheets]

I HAVE EXPLAINED MY ISSUE IN THE BELOW SCREEN SHOTS. PLEASE SEE
THE SCREEN SHOTS AND GIVE YOUR INPUTS


Thanks & Regards

M. Praveen

Accepted Solutions (0)

Answers (1)

Answers (1)

UmeshMali4994
Active Contributor
0 Kudos

Hello Praveen,

First, you check within your master recipe your process instruction in simulation mode and make sure it shows correctly.

Second, Instead of the release phase only, Release the Process order first and then release the control Recipes.

Please check below link for detail step of PI sheet and follow the same.

https://blogs.sap.com/2013/05/10/a-beginners-guide-to-pi-sheets/

I hope this information helpful to you.