on 10-21-2009 2:28 PM
Hi
I have run CNE1 for my project and then executed CNE5 to view the results
I can see that BCWS costs and BCWP costs have all been calculated correctly and are output correctly in CNE5.
However the fields BCWS Qty and BCWP Qty are all blank
Does anyone know why this is?
How can I ensure that BCWS Qty and BCWP Qty values are displayed in CNE5
Thanks
Steve
Hi
I got the BCWS Qty / BCWP Qty & BAC Qty to work by adding a UoM of H on the value category used for EVM
I also got the ACWP Qty to work by adding the UoM H to the value categories used for labour
I also ran CJEN, re-copied the plan costs between Plan version (using CJ9FS) and then ran CNE1 for the project
BCWS / BCWP / BAC & ACWP Qty's are now all populated
Hope this helps others
Regards
Steve
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Stephen,
Could you please explain this "I got the BCWS Qty / BCWP Qty & BAC Qty to work by adding a UoM of H on the value category used for EVM". We always use % as UM for EVM value categories, Do I have to create new value categories with H as UM or change the existing value categories from % to H, Please through some more light on this.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.