Former Member

First piece Inspection

Dear Gurus,

My client is plastic cotainer manufacturer. When they take change over for container size or shape they take first O.K. piece & maintain results for this first O.K. piece. This piece is preserved till the First O.K. pieceof same product for next change over is produced. These two pieces then compared for properties & previous first O.K. piece is then used . How can we map this scenario so that automatic lot will be generated for first O.K. piece. Can we use physical sampling or we have to generate manual lot.

Regards

Amit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Oct 21, 2009 at 10:17 AM

    Dear Amith

    How about using the manual inspection lot (89) . Keep 2 inspection operation in the inspection plan one for the first ok piece and second for the change over piece.

    Let me know your feedbak

    Regards

    Gajesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Gajesh,

      Is there anyway so that we can automatically create an inspection lot for first piece inspection.

      Regards

      Amit

  • avatar image
    Former Member
    Oct 21, 2009 at 11:30 AM

    Hi

    Clear the requirement is there any initial lot like (04,03) ? if yes then pl crate the inspection plan with operation 10 and 20 with previous ok and after change oevr and during RR record the results for both operation and take UD. pl reply for better clarity.

    Cheers

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Rahul,

      This will be the first piece that will be checked once production starts smoothly after setting all machine parameters. Afterward inprocess & final inspection will be done.

      Regards

      Amit

  • avatar image
    Former Member
    Oct 22, 2009 at 07:45 AM

    Dear Amit,

    As there is no triggering event for creating inspection lot, it will be better to create manual inspection lot. As you are preserving the OK piece for later change over comparison, Use sample drawing procedure so that you will be having trace of the physical sample(with Unique sample id).

    Hope this will help you to map the procedure. Do let us know your feedback.

    Thanks

    Saurabh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 18, 2009 at 11:10 AM

    Thanks to all of you for your suggestions.We have decided to create manual inspection lot.

    Regards

    Amit