Dear PP Experts,

currently we have practice as follows:

Produciton order GR & Confirmation processes as an independent process.

We want to control the system in such a way that without material consumption,

GR should not takes place.So that we can have a control on BOM components stock as well and

finished goods stock.

1.CO11N - We are confirming the order

2.COWBPACK - We are creating Handling unit and GR in one shot.

Please provide the solution how to restrict in our case.