Dear PP Experts,
currently we have practice as follows:
Produciton order GR & Confirmation processes as an independent process.
We want to control the system in such a way that without material consumption,
GR should not takes place.So that we can have a control on BOM components stock as well and
finished goods stock.
1.CO11N - We are confirming the order
2.COWBPACK - We are creating Handling unit and GR in one shot.
Please provide the solution how to restrict in our case.
Regards
Don