on 10-16-2009 11:21 AM
I have a planned order. The header material of planned order contains bulk material as a component. When I convert this planned order to production orderI am getting another screen which is ment for creating a purchase requisition for the bulk material. In this screen system is asking for requisitioner name and tracking number. I dont want this screen to come, how to avoid it. How is it coming. There is no external operation control key used.
Check in the BOM item category of this material.
If it is non stock this could be the reason.
Mario