how to release of Committed Cost in SAP?

Dear Experts,

We have a purchase order quantity is 10000,but we only issue invoice 6000, another 4000 we will not issue invoice,because when we create purchase order,WBS has committed cost,how to release 4000 occupy committed cost?

can we tick the flag of "Final invoice"? i have see the help of "Final invoice" it seems ok,but i have test in sap ,it is not ok,

could you please tell me how to use final invoice?

Best Regards,

Merry

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 16, 2009 at 10:33 AM

    Hi,

    If possible, set the activity or the WBSE to status TECO.

    That will make commitments to ZERO.

    Thanks

    Saikishore.Ganga

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 19, 2009 at 07:53 AM

    anyway,thank you very much.

    Add comment
    10|10000 characters needed characters exceeded