on 10-12-2018 1:10 PM
I have noticed that when you performed a block transport, it will move all transports regardless of the results. Is there any options on which if a transport resulted to an RC8 status, it will discontinue the process of importing the rest of the transports? Like if there are 5 transports, if the 1st or 3rd transport resulted to RC8, it should stop and discontinue in importing the remaining transports. Thank you in advance.
Hi,
please check if the parameter STOPONERROR would be helpful. It is a system parameter. Details are available in here: https://help.sap.com/viewer/4a368c163b08418890a406d413933ba7/7.4.19/en-US/3dad5bcf4ebc11d182bf0000e8...
Kind regards
Karin