on 10-10-2018 8:09 PM
Hi Team,
Right now what we see is when MRP runs , 2 purchase requisitions are created to cover . One to cover the safety stock and the other to cover the forecast .
Is there a way to combine the requisitions into 1 at the time of MRP run.
Regards
Nevin
Hello,
What is lot size of the material?
Did you try with perodic lot size like MB ?
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nevin
Could you please check the Forecast requirement date ?
Safety stock is always considered as current/immediate requirement & if the forecast requirement is in future date, then the System will generate 2 separate purchase requisitions, one for the Safety stock & the other for the forecast. Kindly check revert back.
Many Thanks for the feedback. Best Regards : Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.