Hi Gurus,

Client wants to make Info record and source list mandatory for PO creation?

If Inforec and source list not available for that material, then user can't able to create PO.

How can I achieve this requirement?

Any user exit available?

pls help..

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Oct 14, 2009 at 06:48 AM

    Hi ,

    SproMM-Purchasing -Source ListDefine Source List Requirement at Plant Level

    If u mark the indicator then the Source list is mandatory for all the materials procured.

    If u want for a speciic material , mark it in purchasing view of Material Master.

    Inorder to create a source list , inforecord is mandatory -- this is by default Standard SAP .

    Regards

    Ramesh Ch

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Ramesh,

      Yes u r correct when i try to fix vendor or even when i try to maintain MRP relevant systemasks for info record.

      But my concern is even i can maintain source list without these two selection.

      So thr may be cases these two are not required in that case the solution dont solve the issue.

      please advice

  • avatar image
    Former Member
    Oct 14, 2009 at 07:30 AM

    As per my knowledge, if you have maintain source list at plant level...then if you try to maintain PO without maintaining Source list, the system will not allow you to create PO, untill and unless you create Source list for that material...>This is SAP standard Function.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 14, 2009 at 07:49 AM

    Yah ,

    Ustav is right.