cancel
Showing results for 
Search instead for 
Did you mean: 

Creating of PR automatically in background when we RUN the MRP

Former Member
0 Kudos

Hi ,

I want to know is there any setting required for creating the PR automatically in background whenever we RUN the MRP , if it required some setting what are that settings.

regards,

zafar

Accepted Solutions (1)

Accepted Solutions (1)

srinivas_k23
Active Participant
0 Kudos

Zafar,

When you talk about PR, it is always for procurement of a material (that can be inside or outside). But the procurement process can be initiated through PR first natuarally. But PR can be created manually and also Automatical (i.e, system generated when a MRP is carriedout).

For that the following is required to maintain (in the MMRecord):

--> Flag /Check the box of Automatic PO ( a field which is present in the Purchasing View of Material master record)

--> Maintain Purchase Group in the Material master record

--> Maintain MRP Views for the material master record

Certainly PR can be created automatically when MRP is carriedout.

Hope this will clarify your query,

With Metta,

Srin

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks Pradeep and Srin

pardeep_malik
Active Contributor
0 Kudos

Hi,

As per MRP Profile, system will create PR or Planned Order.

In SPRO --> MM --> consumption Based Planning --> Carry out Over All maintenace of MRP Group

Give the Name of the Plant and after that MRP Group 0000 - External Procurement

Here Go creation Indicator ......

Create Purchase Req. 1 Purchase requisitions

While RUN MRP, system will create tha PR for that Plant instead of planned order

Hope Help U !

Regards,

Pardeep malik

jasonm2
Contributor
0 Kudos

Yes, MRP either creates planned order or preq depending on settings like open period, firmed elements, resheduling horizon and variants of MD01.