on 10-12-2009 6:49 PM
Hello,
I'd like to know what the standard is for sending a PO Change to a vendor. We are setting up a web services Procurement document exchange with our vendors and I was wondering if there is a standard business opinion on how much of the PO Header and Line item data is sent to the supplier on a PO Change?
Scenario:
A PO with 5 line items is created.
1. Just some header data changes. Do we resend just the header? Or do we resend the entire PO?
2. Just a line item changes. Do we resend the entire PO? Or maybe the entire header and only the line that changed? Or maybe just the PO number (header) and the line item that changed?
Thanks,
Matt
I plan to test in our Development system. I just wanted to know if there was an industry standard for this process.
It looks like there isn't a standard for this...
Thanks,
Matt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you tried to simulate the situation in DEV environment?
Thanks and Regards,
Abraham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.