Scheduling Agreement with PIR

Former Member
0 Kudos

Dear All,

I have a PIR with 2 validity period. 1st with 01.10.2009 to 14.10.2009 as Rs 100 per Pc & 2nd with 15.10.2009 to 30.10.2009 as Rs 90 per pc. I have a schedules as 100 Pcs on 12.10.2009 and another 100 Pcs on 22.10.2009.

When i do the GR on 22.10.2009 system will pick which price ?

regds,

CB

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

The price will be picked during the GR based on the Price date category you maintained in VMR/PIR/Scheduling agreement not based on the validity period.

Hope it helps

Thanks/Karthik

Former Member
0 Kudos

Hi

There is a relation between PIR price and GR posting if you maintain the price date category as 5 - GR date then the price will be picked from the PIR for valuation on GR date.

Thanks / Karthik

Former Member
0 Kudos

Hi,

Can u please explain me a bit more ? Where i need to maintain the price date category as 5 - GR date ?

Thanks , Issue solved

regds,

CB

Edited by: Kallumama on Nov 4, 2009 3:05 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

The PIR price will be cpatured at the time of creation of PO/SA..

and at the time of MIGO the Price from PO/SA will be picked up..

there is no relation between PIR price & MIGO posting..