on 10-12-2009 3:02 PM
Dear All,
I have a PIR with 2 validity period. 1st with 01.10.2009 to 14.10.2009 as Rs 100 per Pc & 2nd with 15.10.2009 to 30.10.2009 as Rs 90 per pc. I have a schedules as 100 Pcs on 12.10.2009 and another 100 Pcs on 22.10.2009.
When i do the GR on 22.10.2009 system will pick which price ?
regds,
CB
Hi
The price will be picked during the GR based on the Price date category you maintained in VMR/PIR/Scheduling agreement not based on the validity period.
Hope it helps
Thanks/Karthik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The PIR price will be cpatured at the time of creation of PO/SA..
and at the time of MIGO the Price from PO/SA will be picked up..
there is no relation between PIR price & MIGO posting..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.