I think I've tried every possible variation to bring the appropriate CTR/WBS costs. Here's what I'm trying to do:
1. See in one reprt both the CTR planned costs and the WBS planned costs where the cost center is assigned to the WBS as a responsible CTR.
2. Added the characteristic "Import CTR Data" into either a row or general data selection as well as adding object types WBS, ACT, PRJ, and CTR.
3. I can get the WBS to display as a line item with the planned costs, but when I do it changes the credit balance on the CTR to a positive value. This is after I run plan reconciliation for the CTR, and I have integrated planning turned on.
Example:
Postings:
WBS Labor CE: $100
CTR Labor CE: -$300
Report:
Total CTR LAbor balalnce $100
WBS displayed with $100.
When I remove the WBS and Import CTR Data i get the $-300 balance on the CTR. So I'm guessing it's not possible to bring these two objects into the same report to show the CTR over/inder absorption with WBS visibility.
Any suggestions would be appreciated.
Jim