Poject Settlement issue - WBS to WBS

Hi Experts,

I am getting problem while settlement of the customer projects (Fixed Bid and T&M). Can anyone please help me. The details as follows :

Project has the below structure :

Project def

Top level WBS

Network linked to top level WBS

Second level WBS1

Activity1

Activity2..

Second level WBS2

Activity1

Activity2..

Now i have settlement rule on Activities as respective 2nd level WBS

And i have Settlement rule on 2nd level WBSes as Top Level WBS

Top Level WBS is the only Billing Element and it has Settlement Rule to PSG

When i run the settlement, it settles activities to the 2nd Level WBSes, but the costs on the 2nd Level WBSes stays there. The settlement of 2nd level WBSes to Top Level WBS is not happening.

When i searched SAP Customer Messages, i find that the customers faced this problem and referred some SAP note and the problem was resolved. But the SAP Note# is not mentioned.

Please help me. Thanks for going through the lenthy description !

Rajesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 12, 2009 at 08:01 PM

    Hi Virendra,

    Thanks for helping me.

    I did change :

    1. OPSC to have no Settlement Profile

    2. OPUV to have Strategy 05 and no Defualt Rule

    Created new project, posted Costs/Reveues, run Results Analysis. While settlement through CJ88, the system gives error :

    Sender NWA XX Activity 0010

    Maintain Settlement rule of the Sender

    But it did execute settlement for the Level 1 WBS correctly. Same message for all the activities. Can you please help.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Virendra Pal

      This works fine. Successfully settled and closed the project. The settlement is always depends on how te financials handled by the business and it vaies. For my case, there are some manual steps involved.

      Thanks Virendra.

  • Oct 10, 2009 at 08:41 AM

    frankly for customer projects I cannot see any reason to settle from within project objects

    the aim is to get the profitability to PSG via the biloling element

    this means that settlement profiel should be " can be settled"

    only level 1 WBS element billing element needs a settlement rule to PSG

    No other settlement is required - as all cost will be seen at the top level WBS and the revenue is also posted at top level WBS the system will be able to transfer the profitability to PSG

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 11, 2009 at 02:05 PM

    Hi Virendra,

    Understand and thats exactly what i am trying to do. The problem is the activities are having settlement rule for WBS and they take the WBS they belong to at the time of settlement which is 2nd level WBSes. Now

    1. either i need to change the settlement rule at activities to have 1st level WBS and not 2nd level WBS. Do you know what settings i can use to get this ?

    2. or Settle 2nd level WBS to 1st Level. but as you said this doesnt look like needed.

    Please help.

    Thanks

    Rajesh

    Add comment
    10|10000 characters needed characters exceeded

    • you need to remove the settlement from network activities altogether - this can be done from the network type configuration (txn OPSC) make sure that the settlement profile you enter is "can be settled" - settlement profile is configured elsewhere, you may also leave this blank as no settlement is required anyway.

      In transaction OPUV network parameter for network type enter 05 for strategy - No settlement rule and also leave default rule as blank

      This should take care of the networks activity

      Settling WBS level 2 to level 1 is also not required.