on 10-08-2009 5:53 AM
Hi All
I want to do rounding in the existing unit of measure. e.g. my requirement generated is 33 EA and 1 Pac = 10 EA. If i take PAC as ordering unit, system creates PO of 3 PAC. This is fine absolutely. I want rounding in base unit of measurement. e.g. requirement generated is 33 EA. I want to fix EA as ordering unit and PO qty should be rounded to 30 EA.
I mean if i take alternative UOM as ordering unit, it works fine. If my base UOM and ordering UOM is same, rounding doesn't take place.
Is it possible to do rounding at UOM in which requirement got generated??? Requirement generated in EA, and i want to do rounding at EA not PAC.
Gud answer will be awarded fully.
Regards
Kapil
You can do this using Rounding profile. This can be maintained in the material master MRP1 view- lot size data. Secondly you can also maintain it in the Info Record if you want different values vendor wise.
From SAP help
In Customizing, enter a threshold value from which the system should round up to the next value per deliverable unit:
+If the requirements value exceeds the first threshold value, the system always rounds up to the next multiple of the level found
If the requirements value falls below the first threshold value, the system copies the original requirements value.+
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.