Hi Experts
I have created PIR for a material . And when i run MPS ( MD41 ) and check the Stock list (MD04)
Planned orders are not created . System shows independent requirement for the same qty.'
The MRP type Used in Material master is M3 with planning time fence of 1 day.
Can anyone throw light on it why system is not generating Planned order.
There is no stock for the material.
Regds
Rakesh
RAKESH,
WHAT PLANNING STRATEGY R U USING? I TESTED WITH PS=40 & IT WORKS FOR ME.
tHANKS,
RAM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
can you check material status? and also you can check the error message in MD05.
Srinivasan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.