on 10-07-2009 10:14 AM
Dear all,
I am getting an error while BOM transfer using CN33.
A FERT material has its bom.
When i transfer the BOM of that FERT to the project, FERT material is not getting transferred, however all the below level materials are getting transferred on the project.
Kindly help.
sudhir
hi,
i have tried selected the multilevel also still the problem exist.
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One suggestion.
Create 3 to 4 activity having Electrical assembly with reference point E, Mechanical assembly with reference point M, Delivery to warehouse with reference point R i:e you FERT material.
You might be created BOM having mechanical bom electrical bom with respected reference point as mentioned above & the FERT material will be having reference point R.
When you transfer the BOM of that FERT having reference point R to the project, FERT material transferred to activity Delivery as reference point is given R, however all the below level materials are getting transferred on the project with respected reference point.
The quantity of BOM will be multiplied with the execution factor which you need to maintain in network activity.
The FERT material will be shown as negative qty in requirement qty
Hope you got it.
Regards,
ahs
Hi Ansar Shaikh,
I've tried a similar processes many times.
I used Tcode CS02 to assign the reference points to the items and the Tcode CN33 to make the transfer and to choose the reference point of the BOM header. I've tried using different reference points for the items and for the header and using the same.
It must be some step or customization setting I'm missing... Any idea?
shrikrina,
When i said i have entered the data in Change view assembly item/WBS element assignment BOM transfer' screen means i have entered the data in transfer screen of CN33. Still only child items are getting transferred and the assembly item is not getting transferred.
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitin/gokul,
I have already assigned the Project defination with the material and plant & given reference point in Change view assembly item/WBS element assignment BOM transfer' screen.
But still assembly item is not getting transferred to the project, the expected result is that the assembly item required to be transferred as negative quantity where as child item to be transferred with positive quantity.
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sudhir,
I am not at system, But in CN33 Tcode when ever you exeucute at that time, it will transfer only child component only and not Header ( zero Level BOM ) One of this is the scenario of Finish Good will be at Saler order level & belwo level componenet you are assigning via BOM Transfer.
But when you wanted to create assembly from Network at that time you click on Transfer button. It will tansfer BOM header with negative requirment & Component with positive requirment.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear gokul,
The problem is that while BOm transfer level Zero of the BOM is not getting considered.
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.