Alignment to finish date

Hi,

I have assigned materail and want to copy the finish date to the material requirement date.However though the " align finish date" indicator i son still the date is the start date of the activity. How to mak ethe changes to align finish date or delivery date as mentioned in material master.

Edit--


component--


align finish date or Transfer deliver time.

Still there is no change.

Zinni

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Oct 07, 2009 at 10:38 AM

    Try scheduling and see whether date is getting changed to Finish date or not

    Add a comment
    10|10000 characters needed characters exceeded

    • It is used to determine or adjust activity duration as per the lead time of all material components assigned to it. for that select the activity to which material components are assigned, then goto component overview for that activity, then select those material components whose lead time should determine the activity duration and then select Edit>Component>Transfer delivery time, You may note that duration of activity changes..

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.