Hello everybody,
can u tell me which alternative of a BOM will be choosen during the BOM Explosion in a Subcontracting PO (Item Cat. L) - or where the corresponding customizing or master data settings can be done?
many thanks,
Gregor
Hi
BOM explosion in Subcon PO will be carried out automatically when you select the item category L.
If you want to control the BOM selection based on the Alternative then you can go with Production version option and get the help from PP consultant to create the production version.
Assign the production version in Subcontracting Inforecord.
Click the BOM explosion button the switch to alternative BOM during the PO creation.
Hope it helps
Thanks/Karthik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.