2LIS_04_P_MATNR and GLTRS

purvang_zinzuwadia
Active Participant
0 Kudos

Hi Experts,

Its a strange situation. I have one process order which is showing GLTRS as 3/3/2009 in AFKO but when I extract this order (after filling up setup table for full load) using 2LIS_04_P_MATNR the record doesnt bring the same date; instead in the field "Scheduled Finish Date" it displays date 2/25/2009.

when I see in Tx COR3 date 2/25/2009 is schedule start date.

Can anyone help me on this?

thanks,

Purvang

Accepted Solutions (0)

Answers (2)

Answers (2)

purvang_zinzuwadia
Active Participant
0 Kudos

.

purvang_zinzuwadia
Active Participant
0 Kudos

any idea over this?

thanks,

Purvang

purvang_zinzuwadia
Active Participant
0 Kudos

Solved issue in enhancing datasource, adding new fields for mismatched dates, used customer exit to read dates from tables