cancel
Showing results for 
Search instead for 
Did you mean: 

warning message at purchase requisition

Former Member
0 Kudos

friends,

i created internal order and assigned some buedget and relavant setting, in purchase requisition, i have selected internal order and when i try to save it is accepting without giving any warning message, i want to restrict the user to not to post if the PR cross the budget.

regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

To get the warning or error message, tolerance limits needs to be maintained for the controlling area and make sure that the budget settings are properly maintained.

The path to maintain the tolerance limits is IMG--> Controlling->Internal orders->budgeting & availability control->define telerance limits for availability control.

Former Member
0 Kudos

hi,

thanks for reply, but i already did before 90%

regards,

Answers (0)