Dear Guru's,

I have capacity of 7hrs daily, i have order of 700nos, which is taking 70hrs., and available capacity is 70hrs.

After MRP run, back scheduling, system will calculate and distribute as per available for 70hrs, 7hrs daily excluding holidays.

Now if i have order of 1000nos, which is taking 100hrs, and available capacity is 70hrs.

After MRP run, system distribute the capacity with backward scheduling and on order start date it will show overload of 40hrs.

1) If we have to distribute the overload on all working days within the scheduled days only.

2) This overload if we have to distribute on holidays by means of overtime, how to map this?

3) How to plan for non working days capacity without defining new calender.