Oct 06, 2009 at 02:12 AM

Order finish date is later than the required date,why?

28 Views

Hello all.

one trading goods has a required date 2009-12-22,and it's planned delivery time in master data is 30 days same as in the info record ,while GR ProcTme is 0,but in view of /md04 ,I see the Order finish date is 2009-12-25 ,which is later than the required date (2009-12-22) three days,but it's start date is right (2009-11-23),

From 2009-11-23 to 2009-12-22 is 30days( planned delivery time),that is right.

so why the SAP provides the available date (2009-12-25) later than the required date (2009-12-22),the planned delivery time is not to long (only 30 days) to exceed the current date(today is 2009-10-6),so the required start is not in the past,now is 2009-11-23,so what is the reason?

Any advice is welcome!

Thanks,

Helai