Oct 05, 2009 at 04:05 PM

Dep.req. with usage probability

98 Views

Dear guru's,

We try to setup a working variant configurator, but we are not able to get the dependent requirements right.

We use planning strategy 56, we have a superbom with all possible components, the BOM items have a selection condition based on class 200.

We also have a configuration profile and a planning profile. IN MD61 we are able to enter the usage probabilities.

The result however is disappointing: the planned orders generated by MRP show that the full qty is passed on to the components instead of the part as defined in the usage probablity.

Any thoughts? Your help will be greatly appreciated!

Thanks, Albert-Jan