Hello Experts,
Did anyone extract the holiday calendar or factory calendar from S4 as a timeseries to IBP? I'm looking at different tables such as THOL, TFACS but cannot find one with a suitable format for CPI-DS to extract.
Sharing any details on the extraction logic using CPI-DS would help.
Thanks,
Cosmin Pop
Dear Cosmin,
You can use this Function Module: ISU_CHECK_HOLIDAY to check specific day is Holiday/ or Non-Working day.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tin Dinh,
Thanks, I'm aware there are different function modules to check if it is a working day or not but CPI cannot call FMs unless custom abap is used. I'm looking to achieve this with Query transforms and standard CPI functions and to create a timeseries format for IBP for each location.
Cosmin
User | Count |
---|---|
84 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.