i had created a Po for Rs 5 crores and release had effected the PO.

Due to some reasons i changed the Po & vat has included against each item , resulting increase in PO value from 5 to 6 crores.

but despite having all the release strategy configured. The release strategy did not effected.

what would be the reason.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Is your release strategy have any characteristic based on total value?if yes then check what value have been maintained against that characteristic.

Regards,

Indranil

Answers (2)

Answers (2)

lawrei99
Participant
0 Kudos

Hello ,

Please see the characteristic for value if its included and also check the Release indicator "4" is maintained

"Changeable, new release in case of new strat. or val. change " .

By selecting this , if value changes then it will retrigger the release strategy.Please revert back if you have any questions.

raghavendra_praveen
Active Contributor
0 Kudos

Hi

1) check if there is any version generated because of change in PO value. Go to PO header -> version -> accept if there is new version.

2) Also check the release indicator in configuration (MM - purchasing -purchase order -> release procedure -> Define Release Procedure for Purchase Orders -> Release indicator -> indicator should be either 4 or 6.