Hi,

The Semifinished product is manufactured in Plant 1 and it is consumed in plant 2 for making the finished product.

The semifinished product in plant 1 to be planned based on the requirement for finished product in plant 2.

Thanks and regards

murugesan

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member698542
Active Contributor
0 Kudos

I have resolved the issue with special procurement key 70