analysis active availibility control - budget exceeded

Hi Gurus

Can you please advise how could happend excessing of budget also in case of correct setup of tolerance limits(++) and project locking. here are screens from CJ30/CJ31.

[analysis|http://www.picupine.com/pictures/5713-23938.jpg]

[cj30|http://www.picupine.com/pictures/5713-23939.jpg]

Any ideas from Your side in regards to red lines in analysis?

customizing is OK, already tested.

Thanks for help!

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 02, 2009 at 09:44 AM

    I am sorry.

    here are proper links:

    http://www.picupine.com/3d72c93x

    http://www.picupine.com/3d72c93x-2

    thank you for answers

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 02, 2009 at 09:34 AM

    cannot access screens

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 05, 2009 at 11:31 AM

    Hi,

    1) The First Line is the Cost element exempted from AVAC

    2) KAZV:(C): KAZV Down payment clearing

    3) KAZO: (D): Is Down payment

    Down payments are not part of the AVAC.

    Hope it helps...

    Thanks!!!

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.