on 10-02-2009 9:02 AM
We have bom with 2 components B i C and header material A.
BOM contains 3 piece of material B and 1 piece of material C. Both of material have same weight 0,25kg.
In a order our customer want:
A 13 kg 13 pieces
B 9,75 kg 39 pieces
C 3,25 kg 13 pieces
In a stock we have avaible 10 kg of material B and 2,75 of materal C. Delivery was created with this item:
A 11 kg 11 pieces
B 9,75 kg 13 pieces
C 2,75 kg 11 pieces
This delivery is incorrect because of unsynchronized quantities of BOM components. How to synncronize quntity in item B.
Thank in advance
Hi
Try with missing parts
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.