We have bom with 2 components B i C and header material A.

BOM contains 3 piece of material B and 1 piece of material C. Both of material have same weight 0,25kg.

In a order our customer want:

A 13 kg 13 pieces

B 9,75 kg 39 pieces

C 3,25 kg 13 pieces

In a stock we have avaible 10 kg of material B and 2,75 of materal C. Delivery was created with this item:

A 11 kg 11 pieces

B 9,75 kg 13 pieces

C 2,75 kg 11 pieces

This delivery is incorrect because of unsynchronized quantities of BOM components. How to synncronize quntity in item B.

Thank in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Try with missing parts

Former Member
0 Kudos

SHESAGIRI,

Please explain