Inspection type 01 is activated for the material. At the time of creating a GRN, we are creating a GRN with 100 numbers of batches against one GRN. System is creating 100 insoection lots, each inspection lot per batch. Now we want that system should create a inspection lot for 20 batch numbers only though the GRN contains 100 batches ( One inspection lot per batch). Is it possoble? How?

Thanks,

Sachin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 02, 2009 at 05:16 AM

    if you only want to create a lot for 20 batches then you have to create a GR of only 20 nos

    & select Qm view-->Control InspLot you have selected for each material document,material ,batches

    if you have material document of 100 the 100 will be created....so better you split the requirement

    this is only the solution