on 10-01-2009 1:51 PM
Hi All,
I have 2 question here.
I have created a STPO with delivery date say 12.09.2009 from my plant ABC to the Plant XYZ and 140 qty, For this XYZ plant has issued material on 15.09.2009 around 100 qty.,
Now I am looking for the report ME2W to find out what are all the materials has supplied by other plant till 14.09.2009.
but as per the report ME2W it is having I/P option as delivery date, so if i put delivery date between 01.09.2009 to 14.09.2009, it is showing all the material which is issued on after 14.09.2009 also as i have put the delivery date and also it is checking as per delivery date.
Question:
1. How to get these reports ie., materials issued as per issued date or posting date not as per delivery date or not as per material code---- any transaction available for this.
2. one more i come across here in STPO is that, if i create 100 qty of PO but it is allowing to issue more than the PO qty, say if i create Po with 100 Qty but other plant can issue more than 100 ie.,>100.
Is thr any settings available to make such the system should not allow to issue more than the PO qty.
Please help me out on this.
Regards,
Nagaraj S
Edited by: Nagaraj S on Oct 1, 2009 2:52 PM
Hi,
Answer2: when system shows you the warning message, doing double click you can find message number.
Look at custominzing in the following path: Material management --> Purchasing --> Enviroment data --> Define attributes of system messages.
Application area: 06.
Message number: XX
Cat: E.
Regards
Enzo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Nagaraj,
Ans1:
first of all , all purchasing related report will not show the material movement information .... if you want to check material movement then go for MB5B .......
Ans2 : while doing GI for STO more then the STO quantity then system shows a warning message , convert this warning message to error . user wont be able to issue more then PO quantity ....
Regards,
VD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vidya Dewangan ,
I have checked MB5B, it is not for the requirment what i want.
See this report or MB51 would works with only 2 plants where within which these ST can occur.What in my scenario we have more than 2 plants, See i will clearly expalin the situatin -
Thr are 3 plants- Plant A,Plant B, Plant C.
ST happens b/w A and B, A & C, B& C and Visa versa.
Now I want to know what are all the ST happens between Plant A and Plant B, where Plant A has supplied some material to plant B on some day(ie., 351 on posting day),say i dont know material i know only the dates.I cant use MB51, is thr any other report i can get.
Pls help me out.
Regards,
Nagaraj S
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.