on 10-01-2009 11:36 AM
Hi all
Is it possible that system can calculate or update the activity forecost date when i confirm the activity, Senerio is that when i confirm the activity with degree of progress then system will calculate the actual remmening work, I need to estimate the activity forecast date by actual remmening work when i confirm the activiy
thnks
Hi sahmad_77,
There is enhancement CONFPS01, which enable the program to set default value, e.g. forecast date based on your own logic.
Please implement the corresponding user-exit EXIT_SAPLCORF_006.
Kind regards,
Zhenbo