Account assignment category in PO

I have one issue. When i create a PR PO with quality material with material code and account assignment Q , during Goods recciept the material gos to quality inspection. that is fine. But when i create a PR PO with account assignment category P( project) so during goods reciept the material recieved is direcctly consumed to the WBS /cost centre and it is not going in to quality inspection. But i want to activate quality inspection for all quality material with any account assignment category. Can anyone help me in that.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 30, 2009 at 04:27 AM

    Hello

    This is a standard SAP procedure, if you are doing procurement against anyother account assignment other than Q it is directly consumed. Inspection lot will be created but it will not have stock posting tab.