on 09-29-2009 11:10 PM
Hi ,
Here is a scenario with which i need help. I have a material that is MRP planned and subcontracted from a vendor. That material has a component which is planned in APO. When there is a demand on the parent material , it generates dependent demand (Sub Req ) for the component.
Now the problem is the demand at component level (Sub req) is not getting transferred to APO. One way of transferring the Sub Reqs to APO is to put in custom functionality in the PO user exit. But is there any other straightforward way to achieve this without customization .
Please help.
Thanks
Saradha
Hi,
Please check the procurement type on components, and the Inforecord for material.
Do you see transportation lane from vendor to the Plant in APO.
Regards,
Pavan Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.