Source inspection - generate inspection lot at GR

Dear experts,

I need the following:

1) If source inspection is done and UD is accepted --> No inspection lot at GR

2) If source inspection is done and UD is rejected --> Create inspection lot at GR

3) If source inspection is created, but no UD has been made yet --> create inspection lot at GR

By playing with the indicators in Quality Info records and QM control keys, I managed to have the first two scenarios, but the third one doesn't seem to be possible....

Is there any way to ensure my scenario to work? And if yes...How?

thanks,

Philippe

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 30, 2009 at 04:56 AM

    3) If source inspection is created, but no UD has been made yet --> create inspection lot at GR

    In Quality Info records, in source inspection put 01 and do not activate "Source insp.- No G.R." and Iin material master activate QM procurement tick and se control keys to delivery release / vendor release.