on 09-29-2009 8:38 AM
Dear Experts,
I created Production Order.
I issued materials and confirmed activities.
I can see the Actual Cost in the Cost Analysis of the Production Order.
I posted GR against the Production Order. (complete delivery).
When I seetle the Production Order, I can see that FI Document is also getting generated properly.
But, I am not able to see the "Settlement Line" in the Cost Analysis view of the Production Order. The Balance on the Order is not becoming Zero.
What am I missing....
Regards
Hi,
After Settlement (KO88) do Result Analysis (KKA1).This may help you.
Regards,
SVK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Tcodes?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.