FORWARD SCHEDULING IN PROJECT SYSTEM

All,

We are doing forward scheduling in project system. Schedule date update on network properly but on the wbs dates not updated.

Ex.

1.We have WBS MT-2001,That starting date is 09.10.2018.

2.We have four activities,each activities we have duration like 2,4,2 and 2.

3.when we schedule network dates update on the network as starting date- 09.10.2018 and end date 19.10.2018.

4.In the WBS their no end dates update..

Kindly Suggest what should i do?

Add comment
10|10000 characters needed characters exceeded

  • Hi Harshvardhan,

    Which system you are using ECC or S/4 HANA , if you are using HANA then you need to apply some notes on scheduling suggested by SAP . Lets know whether only forward schedule are not working or both forward & backward scheduling are not working.

  • Get RSS Feed

1 Answer

  • Oct 09, 2018 at 01:27 PM

    What are your WBS Scheduling Parameters, Network Scheduling Parameters, and Planning Methods from the Project Profile? They need to be in sync. And how are you performing scheduling? Please provide screen shots.

    Add comment