on 10-05-2018 4:56 PM
Hello to everyone,
Do you know how "Reschedule top-down" and "Reschedule bottom-up" work in production scenario in bydesign?
I need to reschedule the sales order and its production linked for a new date but the reschedule tabs seems to don't work.
What should happens when I click on this tabs?
Any idea?
Thanks
Daniele
Dear Daniele,
When you Click on Reschedule Top-Down system propagate changes from load leveling to affected production proposals on lower levels of the product structure.
Alternatively, when you click on Reschedule Bottom-Up system propagate changes from load leveling to affected production proposals on higher levels of the product structure.
I hope this clarifies.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Sandeep. Do you know if there is any run can do a mass reschedule? The purchase order is normally pushed back for all products on it. Surely users do not want to go into each of component products and manually click this reschedule.