Dear all experts,
please help me on the following issues.
i am working on a capital project. Investment profile is defined and assgined to the project profile.
the top WBS is T-09-001
the second level WBS are T-09-001-01, T-09-001-02, T-09-001-03, T-09-001-04, T-09-001-05 for example.
the third level WBS is T-09-001-05-01.
i do the test settlement when the project status is release. (i didn't maintain the settlement rule.)
the result is that every single WBS is settled to a FXA (the numbers are generated automatically)
for example
T-09-001-01 to FXA 1000/40047/0 30000CNY
T-09-001-02 to FXA 1000/40048/0 40000CNY
T-09-001-03 to FXA 1000/40049/0 40000CNY......
i am not sure if it is correct or not, because it's my first time to deal with capital projects.
if i want to settle all the sub-WBS to top WBS and the top one settled to AUC, how can i do it.
i manually maintain the settlement rule for all the sub-WBS to top WBS and settle the project again.
but the result is the same. i don't know where the problem is.
please tell me how to do it or how to settle the capital projects in most cases?
thanks a lot.
judy
For these type of requirement you can manually give INvestment profile on the Level one WBS Elements only. So, System will create AUC / FXA on level one WBS only. For below level WBS use multi-level settlement. Roll up the cost ot Level one WBS and settle the same from level one to FXA.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Below was something which we had done in such case:
1. Created a substitution rule against the WBS element, if the level of WBS >=2 substitute the Investment profile with 'Blank'. With this when ever you create a project and save it or call the substitution from menu, system would retain the investment profile on level 1 WBS and when project is released only 1 AUC is created for the project which is on level 1 WBS.
2. Settle all other lower WBS to it's parent WBS and you can implement OSS note 211324 - CJB1: Strategy for settlement to superior WBS. Refer the below link about how this works:
http://wiki.sdn.sap.com/wiki/display/PLM/ModificationnoteforStrategyforsettlementtosuperiorWBS
Doing both the above, you would create only 1 AUC (on level 1 WBS) and finally settle all lower WBS to level 1 WBS and from there system would then automatically settle the costs to AUC fixed asset.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.