Multilevel BOM

Former Member
0 Kudos

Hi All,

My scenario is make to order (strategy 20 ) and i am using multilevel BOM . one finish material & 12 semifinish material.

each semi finish having a separate bom. all bom depending on each bom.assign to finish. i run mrp in mrp only one material execute i.e. finish not semi finish as well as raw why?

Thanks,

Parag

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

1) Plz check the stocks of all semi-finished materails (which may be more than required)

2) just check in CS11, CS12 whether BOM is getting exploded

3) in materail master MRP - 4 view for all semi-finished materials field ( MRP Dep. Req - 1 or Blank)

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

There is no stock of semi finish as well as raw material in system.

by t code cs11 all bom are explode clearly.

in material master of mrp 4 view maintain 1 for all semi finish material.

but there is no execute raw material.

Thanks,

Parag

Former Member
0 Kudos

Hi,

in material master of mrp 4 view maintain 1 for all semi finish material

By ur above statment

1) if it is 1, then system will not paln dependent requirments

2) Keep it blank & run MRP, system will creat plan orders for dependend requirments

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

In mrp 4 view ind./ coll. requ. is maintain by blank. run mrp but there is no execute of raw material.

Thanks,

Parag

Former Member
0 Kudos

Dear Parag,

i am specifying the (field - MRP dep.requirements - blank) (not 1)

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

mrp 4 view not maintain by 1 the field is blank.

Former Member
0 Kudos

Dear parag,

1) in MRP-4 View, which field ur talking abt

2) after running MD03, still system is not generating plan orders Then check the stock in MMBE

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

i am talking abt. In mrp 4 view individual/ collective requirement field. there is no stock of material in system.

Former Member
0 Kudos

Dear Parag,

i was talking abt Field

MRP-4 view - MRP dep.requirements- blank

this field is just beside production version

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

Sorry for misunderstanding .

in MRP-4 view - MRP dep.requirements- blank. but there is no effect.

Former Member
0 Kudos

Hi Parag,

1) Plz re-check the stock in MMBE For raw materials

2) just try to Run MRP in MD03 for VB MRP type

3) in MD03, palnning mode parameter, make it as 3 - delete & re-create planning data

then check the result

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

requirement generate for raw material VB type ok. but what abt. PD type.

Former Member
0 Kudos

Dear parag,

For PD type, Run MRP in MD02

just input header materail (FERT) in MD02

and As mentioned in my previous post

mention planning data as 3

then check the result

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

MRP run by md02 for PD type but there is no execution of PD type raw material.

Former Member
0 Kudos

Hi,

For Raw materials PD type for which ur not getting Plan orders

just check the stock (which might be more than required qty)

Regards

kumar

Former Member
0 Kudos

HI Kumar,

there are 30 no. raw material and there is no stock for each material. Which is PD tyep material.

Former Member
0 Kudos

Hi,

Just check in CS11 & CS12, inputting ur header material

whether whole BOM is getting exploded or not

Regards

kumar

Former Member
0 Kudos

Hi Kumar ,

Whole BOM exploded in cs11 ok.

Former Member
0 Kudos

Hi

Do one thing, in MD02 input raw material & Run MRP (MRP Type PD)

and check the result whether system is generating plan orders

Regards

kumar

Former Member
0 Kudos

Hi Kumar,

MRP run by MD02 for PD item there is no planned order generate.

Former Member
0 Kudos

Hi,

is system is throwing any Mssg

so please paste it here

so experts can solve this

by seeing the Mssg

Regards

kumar

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

First check the planning file entry in MD21? If not then create it through MD20 and take MRP run and check it.

Regards,,

R.Brahmankar

former_member196398
Active Contributor
0 Kudos

Parag,

One basic question, Is there a Sales Order for the FERT material and are there planned orders created for HALB materials?

Please provide the complete picture as it stands now,

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

I have already mention in first message. my scenario is make to order . sales order for finish material . there is no execution of planned orders for semi finish and raw material.

Former Member
0 Kudos

Hi,

i have already create planning file entry. but planned order not generate for raw material (PD type).

former_member196398
Active Contributor
0 Kudos

Parag,

Can you please take a screen shot of MD04 for the FERT and HALB materials and provide us the link to understand the current situation.

Regards,

Prasobh

Former Member
0 Kudos

HI,

There is no any message from system.

Former Member
0 Kudos

Dear Parag,

if Possible Do as Mr. Prasobh stated

or else just Creat another one Fert , one Halb & One ROH (multilevel)

then Complete all steps upto MRP

then Run MRP in MD02

Regards

kumar

dhaval_choksi3
Active Contributor
0 Kudos

Hi Parag,

Check whether Dependent req. is generated or not?

This is the prerequisite for getting planning result for BOM components.

If it is not created that means BOM of Fert / Halb is not explod.

Go to MD04 and check dep. req. for raw materials.

Regards,

Dhaval

Former Member
0 Kudos

Hi,

Dependent req. is not generated. total BOM explode in t code CS11 for fert material.

Edited by: parag tatiwar on Sep 26, 2009 11:08 AM

dhaval_choksi3
Active Contributor
0 Kudos

Dear,

See If BOM is explode in CS11 it doesn't means that same thing will be assured during MRP also.BOM selection criteria may be different in both the cases.

If Dep. requirement is not generate then there will be many reasons.

Check in MD04 for Fert / Halb materials for exception msg. and revert back.

Regards,

Dhaval

Former Member
0 Kudos

Hi Dhaval,

In md04 screen for finish material exception message is 06--- start date in the past

semi finish material exception message is 64---production finish after order finish

Thank

Parag

Former Member
0 Kudos

Hi Dhaval,

In md04 screen for finish material exception message is 64--- -production finish after order finish

semi finish material exception message is 06--start date in the past

Thank

Parag

Former Member
0 Kudos

Dear Parag,

1) As per ur post, it's Clear that dependent requirments have been created for header material

2) for header materail u are getting Excetion Mssg & For Semi-finished Also

3) so i think system behaving perfectly

4) Now here only point is for which matrials, MRP is nor Creating Proposals means, This materails have Been Planned By VB

Regards

kumar

Former Member
0 Kudos

Dear Kumar,

There is no executing planned order of raw material which MRP type is PD.also no executing of semi finish material.

Thanks

Parag

Former Member
0 Kudos

Hi,

if ur semi-finished is not Getting planned, then what is meant by ur below Mssg

semi finish material exception message is 06--start date in the past

Regards

kumar

Former Member
0 Kudos

Dear Kumar,

Out of 12 semi finish material only one semi finish material are execute. that material have exception message 06.

Thanks,

parag

Former Member
0 Kudos

Dear Parag,

i think all Forum Members, have tried there best to solve ur issue

As No one can View ur System, so just Do as Mr. Prasobh stated

As this Thread has become so long, So Plz close it & open a new one

All The Best

Regards

kumar

Former Member
0 Kudos

hi,

Close it.

former_member196398
Active Contributor
0 Kudos

Parag,

Execute MRP using MD02 transaction and let us know the results. This can also because the stock level of the semifinished and raw materials are enough to exeucte the current sales order demand as these Semi-finished and raw materials are maintained with "2" - Collective Indicator in MRP4 view.

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

I have maintain all semi finish as well as raw material individual/ collective requ. 2. and run mrp by t code md02. only semi finish material execute not raw.

Thanks,

Parag

former_member196398
Active Contributor
0 Kudos

Parag,

What is the MRP type of the raw material? If it is consumption based planning then please mention the re-order point and other parameters maintained

What is the current stock and requirements+reciepts for this raw material?

Regards,

Prasobh

Former Member
0 Kudos

Hi prasobh,

mrp type of raw material having both i.e. some material pd type & some material vb type. also reorde point mentioned of vb type.

there is no stock of raw material and requirement of all raw material is 10 no.

Thanks,

Parag

former_member196398
Active Contributor
0 Kudos

Parag,

Please run MD03 for the raw material as the dependent requirements from semifinished material are not valid since the raw material is of VB MRP type.

Regards,

Prasobh

Former Member
0 Kudos

Hi Prasobh,

Having those material mrp type is vb run by md03 but there is no requirement after mrp.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

First check the planning file entry in MD21. If it is not available for these material then create it through MD20 or OMDO.

After that take MRP run FOR VB use md01 or md03.

Regards,

R.Brahmnkar

Former Member
0 Kudos

Hi ,

some material having planning file entry and some not for vb type. but those material having mrp type pd that also not execute in mrp. only for raw material.

Thanks,

Parag